Mandeville Extension and Rebuild Details
|
Basic building costs £/m2. |
£2000m2 |
|
Services cost £/m2. |
£827m2 |
|
External works cost £/m2. |
£47m2 |
|
Gross floor area. |
700m2 |
|
Total area of the site. |
33000m2 |
|
Function area and their size. |
|
|
Area of circulation. |
138m2 |
|
Area of storage. |
44m2 |
|
% of grounds and /or building used by the community |
|
|
Predicted electrical consumption kWh/m2. |
22.94 kWh/ year/ m2 |
|
Predicted fossil fuel consumption kWh/m2. |
|
|
Predicted water use m/3 person/ year. |
15 litres of hot water per day per pupil |
|
% of water provided by rainwater or greywater. |
There is no rainwater harvesting |
|
Steps taken during construction to reduce environmental impacts |
|
|
List of social or economically sustainable measures achieved. |
|